SCOPE OF WORK (SOW)
VAMHCS Yearly Aboveground Storage Tank (AST) Inspections to Comply with Section 112.7(e) of the Clean Water Act and Maryland Department of the Environment Oil Operations Permit, Code of Maryland Regulations (COMAR) 26.10.01-.12; 26.10.01.16-.21 and 26.10.15
2
I. INTRODUCTION
As required by Section 112.7(e) of the Clean Water Act and Maryland Department of the Environment Oil Operations Permit, Code of Maryland Regulations (COMAR) 26.10.01-.12; 26.10.01.16-.21 and 26.10.1, the VAMHCS must Conduct yearly aboveground storage tank (AST) inspections and tests. This is detailed in each VAMHCS Facility s Integrated Contingency Plan (ICP). The annual inspections will conform to the Steel Tank Institute SP-001, Aboveground Storage Tank Inspection Standards and will be conducted using the annual inspection checklist included in each VAMHCS facility s ICP. The VAMHCS would like a base plus four option years best value annual AST inspection contract.
II. DESCRIPTION OF WORK
Contractor will perform yearly AST inspections as detailed in each VAMHCS Facility s Integrated Contingency Plan and applicable Oil Operations Permit(s). This includes approximately 43 shop-fabricated tanks and day tanks ranging in size from 55-gallons to 15,000-gallons and 1 field-erected tank with a capacity of 150,000-gallons. See Appendix A.
The annual inspections shall conform to the Steel Tank Institute SP-001, Aboveground Storage Tank Inspection Standards and will be conducted using the annual inspection checklist included in each VAMHCS facility s Integrated Contingency Plan as well as any additional requirements per each VAMHCS facility s Oil Operations Permit (if applicable). This will include ASTs located at the following locations per the latest version of each VAMHCS location s Integrated Contingency Plan:
Baltimore VAMC, 10 North Greene Street Baltimore, MD 21201
Loch Raven VAMC, 3901 The Alameda Baltimore, MD 21218
Perry Point VAMC, 101 Boilerhouse Road, Rm. 40 Perry Point, MD 21902
b. VAMHCS Site Oil Operations Permit(s) also stipulate additional annual inspection requirements for vaulted tanks. The site permit(s) require an annual inspection of the vaulted area of the tank, which is considered a confined space under the Occupational Safety and Health Act (OSHA) at 29 CFR 1910.146(b). Contractor will operate in accordance with its internal Confined Space Permit Program. A properly calibrated multi- gas meter to inspect the atmosphere of the space prior to entry required. In accordance with the VAMC Site Oil Operations Permit(s), the contractor will also submit a copy of the inspection results to MDE within 15 business days of completing the inspection.
c. ASSUMPTIONS:
A MD licensed PE and STI certified personnel for SP001 Aboveground Tank System Inspector will oversee the tank inspections
Offeror must show past performance inspecting ASTs in the state of MD
Offeror must have an office within the tri-state area of MD; PA; or Virginia/Washington, D.C.
Yearly AST inspections as detailed in each VAMHCS Facility s Integrated Contingency Plan and applicable Oil Operations Permit(s); this includes approximately 43 shop-fabricated tanks and day tanks ranging in size from 55-gallons to 15,000-gallons and 1 field-erected tank with a capacity of 150,000-gallons.
Perry Point VAMC personnel will provide timely access to all tanks and tank areas, including unlocking of gates and fill ports as needed.
Contractor will be able to work onsite each day for 8-hours.
A total of 8 days onsite is assumed for completing Perry Point VAMC
A total of 1 day onsite is assumed for completing Baltimore VAMC and
A total of 1 day onsite is assumed for completing Loch Raven VAMC.
Appropriate personnel and monitoring will be provided during the confined space entries, when needed.
The contractor will supply an 8-foot, A-frame ladder to access tank tops. For tanks taller than that for which a catwalk, access platform, stairs, or other safe means of access are not present, contractor will complete as much of an inspection as can be done safely. Anything that cannot be inspected will be noted in the report.
III. SPECIFIC WORK ITEMS
The contractor shall complete yearly AST inspections using the latest list of ASTs in each VAMHCS facility s Integrated Contingency plan as well as using the latest yearly AST inspection checklist provided in each facility s Integrated Contingency Plan. This will include (but is not limited to):
An initial kick-off meeting to discuss access, facility rules and specific needs for tank access; documentation; etc.(this may be done virtually or in-person)
The Contractor must develop/update each yearly inspection form for each VAMHCS AST.
The Contractor also provide electronic copies of each yearly inspection form for each VAMHCS AST.
Provide a list of deficiencies including repairs needed and estimates to complete repairs/deficiencies for each VAMHCS AST to be compliant with all applicable laws and regulations to include (but is not limited to):
Section 112.7(e) of the Clean Water Act,
Each VAMHCS Facility s Integrated Contingency Plan.
Each VAMHCS Facility s Oil Operations Permit
Steel Tank Institute SP-001, Aboveground Storage Tank Inspection Standards
COMAR Subtitle 10, Oil Pollution and Tank Management
IV. PROJECT MILESTONES/SCHEDULE
The period of performance for each option year will be 365 days from the notice to proceed.
The following schedule shall be adhered to in completing this work effort:
V. PROJECT SUBMITTALS:
1. Draft Annual AST Inspections for each VAMHCS facility listed above for each AST listed in the VAMHCS facility s Integrated Contingency Plan: One electronic copy should be sent to the COR. The COR will then review this and provide comments to the contractor.
2. Draft Annual AST Inspection Comment Resolution: Contractor will address up to 2 rounds of comments from the COR to prepare the final Annual AST Inspections.
3. Annual inspection for Vaulted Tank per MDE Oil Operations Permit(s): An annual inspection of the vaulted area of the tank, which is considered a confined space under the Occupational Safety and Health Act (OSHA) at 29 CFR 1910.146(b). In accordance with the Site Oil Operations Permit(s), the contractor will also submit a final, VAMHCS COR-approved copy of the inspection results for this tank to MDE within 15 business days of completing the inspection.
4. Final Annual AST Inspections and List of required AST repairs/corrections based on observations/inspections, if applicable (for compliance with current laws and regulations): Electronic deliverable will be delivered to the VAMHCS COR for all ASTs at the Baltimore VAMC; Loch Raven VAMC; and Perry Point VAMC.
Milestone
Timeline
Onsite Annual AST Inspections at Perry Point; Loch Raven; and Baltimore VAMCs
Completed within 90 days of Notice to Proceed (NTP)
Draft submission of PP AST D-103 Annual Inspection to VAMHCS COR
91 Days after NTP
COR/VAMHCS review period
2 Days after receiving Draft Submission of
Vaulted AST Annual Inspection
Final Submission of Vaulted AST Annual Inspection to VAMHCS COR and MDE
5 Days after receiving COR comments
MDE Comment Resolution and Response for Vaulted Tank Annual Inspection
2 weeks after receiving comments from MDE
Draft submission of all VAMHCS Facility AST Inspections (with the exception of vaulted AST outlined above) and List of required AST repairs/corrections based on observations/inspections (for compliance with current laws and regulations)
100 Days after NTP
COR/VAMHCS review period
2 weeks after receiving Draft
Final Submission of all VAMHCS Facility AST Inspections (with the exception of vaulted AST outlined above) List of required AST repairs/corrections based on observations/inspections (for compliance with current laws and regulations)
2 weeks after receiving COR comments
APPENDIX A LISTS OF TANKS TO BE INSPECTED PER SITE ICPs as of September 2021. (This list may be updated as ICPs are updated and will be provided to the contractor)
I. PERRY POINT VAMC ABOVEGROUND STORAGE TANKS:
Table A-1. Aboveground Storage Tank Inventory Perry Point VAMC
TANK NO.
LOCATION
CAPACITY
(gallons)
PRODUCT
HI-LEVEL ALARM
CONTAINMENT AND SPILL CONTROL FEATURES
D-17H
Kitchen,
Bldg. 17H
3,000
Diesel Fuel
Yes
Double-walled tank, overfill
prevention device
DT-17H
Emergency Generator, Bldg.
17H
100
Diesel Fuel
Yes
Integral Secondary Containment
D-19H
Medical Ward,
Bldg. 19H
2,000
Diesel Fuel
No
Double-walled tank
D-20
Raw Water Pumping Station,
Bldg. 20
605
Diesel Fuel
No
Double-walled tank, Secondary containment
D-20H/D-333
Generator Bldg. 333, adjacent to
Bldg. 20H
2,000
Diesel Fuel
Yes
Double-walled tank, overfill prevention device, spill bucket
DT-20H/DT-
333
Generator Bldg.
333
150
Diesel Fuel
No
Double-walled tank
D-23H/D-361G
Hospital Clinic, Bldg. 23 (Outside
Building 23H)
2,500
Diesel Fuel
Yes
Double-walled tank, spill bucket
DT-23H/DT-
361G
Emergency
Generator, Bldg.361 G (Outside Building 23H
75
Diesel Fuel
Yes
Double-walled tank
DT 23H/GG106
Room GG 106, Bldg. 23H (Inside
Building 23H)
75
Diesel Fuel
Yes
Double walled tank
D 103
NEW Water Filter
Plant, Bldg. 103
4000
Diesel Fuel
No
Vaulted, double walled tank,
Secondary containment
DT 103A
NEW Water Filter
Plant, Bldg. 103
242
Diesel Fuel
No
Double walled tank, Secondary
containment
DT 103B
NEW Water Filter
Plant, Bldg. 103
242
Diesel Fuel
No
Double walled tank, Secondary containment
D 311
Wastewater Pumping Station,
Bldg. 311
1,000
Diesel Fuel
Yes
Double walled tank, spill bucket
DT 311
Emergency Generator, Bldg.
311
75
Diesel Fuel
Yes
Single walled tank; secondary containment partially provided by building in conjunction with
active measures
D 315
Boiler Plant, Bldg.
315
150,000
Heating Oil
No
164,000 gallon engineered berm consisting of soil and concrete with a PVC liner
D 321.A
Chiller Plant, Bldg.
321
500
Diesel Fuel
No
Double walled tank, spill bucket
DT 321.A
Emergency Generator, Bldg.
321
75
Diesel Fuel
Yes
Double walled tank
D 321.B
Chiller Plant, Bldg.
321
15,000
Diesel Fuel
Yes
Double walled tank
DT 321.B
Chiller Plant, Bldg.
321
700
Diesel Fuel
Yes
Integral Secondary Containment
D 321.C
Chiller Plant, Bldg.
321
15,000
Diesel Fuel
Yes
Double walled tank
DT 321.C
Chiller Plant, Bldg.
321
700
Diesel Fuel
Yes
Integral Secondary Containment
D 324
Generator Bldg.
324
550
Diesel Fuel
No
Double walled tank, spill bucket
D 325
Generator Bldg.
325
550
Diesel Fuel
No
Double walled tank, spill bucket
D 326
Generator Bldg.
326
550
Diesel Fuel
No
Double walled tank, spill bucket
D 327
Generator Bldg.
327
500
Diesel Fuel
No
Double walled tank, spill bucket
D 329
Generator Bldg.
329
550
Diesel Fuel
No
Double walled tank, spill bucket
D 344
Generator Bldg.
344
550
Diesel Fuel
Yes
Double walled tank; overfill
prevention device
D 360G
Filter Plant, Bldg. 360G
2,000
Diesel Fuel
Yes
Double walled tank, spill bucket
D-365
Generator Bldg.
365
1,000
Diesel Fuel
Yes
Double-walled tank, spill bucket
DT-365
Emergency Generator, Bldg.
365
75
Diesel Fuel
No
Single-walled tank; secondary containment partially provided by building in conjunction with
active measures
D-507
Salt Shed, Bldg.
507
500
Diesel Fuel
No
Double-walled tank
D-11.A
Mobile Emergency Generator (200
kw)
100
Diesel Fuel
No
Double-walled tank
D-11.B
Mobile Emergency Generator (200
kw)
100
Diesel Fuel
No
Double-walled tank
D-11.C
Mobile Emergency Generator (100
kw)
100
Diesel Fuel
No
Double-walled tank
D-Mobile
REMRO (Outside)
Mobile Refueler
275
Diesel Fuel
N/A
None
D-REMRO
Automotive Repair
Garage
500
Heating Oil
No
Sec. containment basin
O-11
Garage, Bldg. 11
275
Used Oil
No
Sec. containment basin
Total # of Tanks Perry Point VAMC
37
II. BALTIMORE VAMC ABOVEGROUND STORAGE TANKS:
Table A-2. Baltimore VAMC Aboveground Storage Tank Inventory
Tank No.
Location
Capacity (gallons)
Product
High-Level Alarm
Containment and Spill Control Features
AST 1
8th floor,
Room 8A-101
300
Diesel Fuel
No
None
AST 2
8th floor,
Room 8A-101
300
Diesel Fuel
No
None
AST 3
8th floor,
Room 8A-101
300
Diesel Fuel
No
None
Total # of Tanks Baltimore VAMC
3
III. LOCH RAVEN VAMC ABOVEGROUND STORAGE TANKS:
Table A-3. Loch Raven Aboveground Storage Tank Inventory
Tank No.
Location
Capacity
(gallons)
Product
Hi-Level Alarm
Containment and Spill Control Features
AST-1
Building 1 (exterior)
2,000
Diesel fuel
Yes
Double-walled steel tank
DT-1
Emergency generator day tank (exterior)
75
Diesel fuel
No
Double-walled
Mobile Generator
Building 1 (exterior)
574
Diesel fuel
Yes
Double-walled
Total # of Tanks Loch Raven VAMC
3