General Information
- Contract Opportunity Type: Combined Synopsis/Solicitation (Updated)
- Updated Published Date: Aug 30, 2022 02:58 pm MDT
- Original Published Date: Aug 19, 2022 08:52 am MDT
- Updated Date Offers Due: Sep 06, 2022 12:00 pm MDT
- Original Date Offers Due: Aug 30, 2022 12:00 pm MDT
- Inactive Policy: 15 days after date offers due
- Updated Inactive Date: Sep 21, 2022
- Original Inactive Date: Sep 14, 2022
- Initiative:
- None
Classification
- Original Set Aside:
- Product Service Code: 9905 - SIGNS, ADVERTISING DISPLAYS, AND IDENTIFICATION PLATES
- NAICS Code:
- 339950 - Sign Manufacturing
- Place of Performance: Colorado Springs , CO 80912USA
Description
The Contractor shall furnish all labor, equipment, transportation, design and materials to remove and replace signage above north side main entrance of bldg. 300. Contractor should account for additional labor hours used to gain access to Restricted Area (RA). For additional information please see the PWS attached. (PWS 300 Signs v2.pdf)
There will be a site visit available on 24 Aug @ 930, we will meet at the visitor center located outside Schriever SFB (1560 Enoch Rd, Colorado Springs, CO 80930) @ 930. You will have to get cleared to get on base so please show up at least 30 mins early so you are able to do that. We will then escort you on to base & in to the RA. You need at least 2 forms of identification to get a visitor badge to get in to the RA, please prepare accordingly.
RFI's will be due to me by 25 Aug @ 1200.
If you have any other questions or concerns please email the contact information below. Thank you.
UPDATE (24 August 2022)
A modification has been made to this RFQ.
1. The PWS has been updated, the size of the font required on the sign has been changed. The changes that have been made are highlighted & underlined in the updated PWS. (PWS 300 Sign v3.pdf)
I will be removing v2 of the PWS from this RFQ to lessen any confusion there may be. If you have any questions please contact the POC listed below.
UPDATE (29 Aug 2022)
An amendment has been made to this RFQ.
1. The RFQ closeout date is being pushed from 30 Aug @ 1200 MST to 6 Sep @ 1200 MST, this is to allow RFI's to be answered more in depth & once posted, allow Contractors to evaluate, ask more questions if necessary, & build their quotes accordingly.
If you have sent in RFI's ensure you receive a confirmation email of receipt from the POC below, if you have not received one yet please re-send your email.
If you have any other questions or concerns regarding this RFQ, please contact the POC below. Thank you.
UPDATE (30 Aug 2022)
An amendment has been made to this solicitation.
1. Four new attachments have been added (B300 Signage Site Visit RFI v4, Space Force Logo Guidelines, MoS 300 Sign, & Space Force Symbol) & an updated PWS has also been added (PWS 300 Signs v4). I will be removing the old version of the PWS to avoid any confusion.
If you have any other questions or concerns regarding this RFQ or RFI answers, please contact the POC below & ensure you receive a confirmation receipt back. Thank you.
Attachments/Links
Contact Information
Contracting Office Address
- ADMIN ONLY NO REQTN CP 719 567 3899 210 FALCON PKWY BLDG 210 STE 2116
- SCHRIEVER SFB , CO 80912-2116
- USA
Primary Point of Contact
- SSgt Cindy Delgado
- cindy.delgado@us.af.mil
Secondary Point of Contact
History
- Sep 21, 2022 09:56 pm MDTCombined Synopsis/Solicitation (Updated)
- Aug 30, 2022 02:47 pm MDTCombined Synopsis/Solicitation (Updated)
- Aug 29, 2022 11:29 am MDTCombined Synopsis/Solicitation (Updated)
- Aug 24, 2022 07:43 am MDTCombined Synopsis/Solicitation (Updated)
- Aug 19, 2022 08:52 am MDTCombined Synopsis/Solicitation (Original)