Fermilab LBNF NSCF Construction - Near Detector Complex RFP
Note: There have been new actions to this contract opportunity. To view the most recent action, please click here.
Looking for contract opportunity help?
APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator (opens in new window) for free government expertise related to contract opportunities.
APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.
The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (opens in new window) (PTAP).
General Information
- Contract Opportunity Type: Solicitation (Updated)
- Updated Published Date: Nov 22, 2024 02:29 pm CST
- Original Published Date: Jun 05, 2024 03:55 pm CDT
- Updated Date Offers Due: Feb 07, 2025 03:00 pm CST
- Original Date Offers Due: Sep 09, 2024 03:00 pm CDT
- Inactive Policy: 15 days after date offers due
- Updated Inactive Date: Feb 22, 2025
- Original Inactive Date: Sep 24, 2024
- Initiative:
- None
Classification
- Original Set Aside:
- Product Service Code: Y1LC - CONSTRUCTION OF TUNNELS AND SUBSURFACE STRUCTURES
- NAICS Code:
- 23 - Construction
- Place of Performance: Batavia , IL 60510USA
Description
The draft RFP contains Instructions to Offerors, Drawings, Specifications, and the Sample Subcontract including applicable documents. Funding Availability and Subcontract Milestones will be provided prior to the Pre-Proposal Meeting.
DESCRIPTION
FRA expects to select one subcontractor to perform construction services of the Near Detector Complex as required by the LBNF/DUNE-US Project, NSCF at Fermilab under a Firm Fixed Price (FFP) Subcontract.
The work shall include all services, labor, material, tools, equipment, excavation, shoring, testing, inspection, and all necessary General Conditions Work that is required by or may be reasonably inferred from the Subcontract documents to provide general contractor construction work for the project. Refer to the Reference Drawings and Technical Specifications in Packages 2 and 3 for more information.
The NSCF Near Detector Complex Construction scope includes a service building, primary and secondary shafts, detector cavern, and site improvements including access road improvements, an equipment yard, a hardstand, and utilities that will house and support the LBNF Near Detector.
The proposals shall be valid up to the anticipated award date, which is 7 months from the proposal due date. FRA reserves the right to reject any and all proposals, to waive any minor irregularities in any proposal, or to cancel this RFP at any time prior to award without cost to FRA. FRA will not reimburse any firm for any preparation costs or any other costs related to the participation in or preparation of this RFP.
MANDATORY PRE-PROPOSAL CONFERENCE
Offerors are required to attend a Pre-Proposal Conference and to inspect the work site on Wednesday, July 10, 2024, starting at 10:00 AM Central Time. FRA will present information about the project, which should be of interest to all Offerors. The conference will be held in the CDF Building 327 conference room. Offerors that do not attend the Pre-Proposal Conference will not be eligible for award and any submissions provided will not be evaluated.
Offerors shall inform the FRA Procurement Specialist (bquinn@fnal.gov) no later than 5:00 PM Central Time on Wednesday, June 26, 2024, of the number and name of persons who will attend the site inspection, including any lower tier subcontractors, and the company they will be representing.
OFFERORS' QUESTIONS
Any prospective Offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request in writing by close of business (5:00 PM), January 15, 2025. Questions submitted after this date may not be answered prior to the proposal's due date. Questions must be submitted by email to bquinn@fnal.gov.
Answers to questions that are germane to the interpretation of FRA’s requirements will be issued to all offerors via addendum, ensuring that the identity of offerors submitting the questions will remain anonymous.
Addendum 1 is issued 6/21/2024 to incorporate document revisions, access information for Pre-Proposal Conference, and questions and responses.
Addendum 2 is issued 7/09/2024 to incorporate questions and responses, information on funding and milestones, and supplemental documents pertaining to a Sample Small Business Subcontraction Plan Template and FRA Illinois Sales Tax Exemption Certificate.
Addendum 3 is issued 7/26/2024 to incorporate questions and responses, sign-in sheets and presentation slides from the 7/10/2024 Pre-Proposal Conference, an updated ES&H document, and extends the due date for questions to 8/15/2024 and the due date for proposals to 9/16/2024.
Addendum 4 is issued 8/1/2024 to incorporate updated information on funding and milestones. Please see the re-issued RFP Letter for anticipated amounts. Additionally this addendum removes the "draft" designation from the documents.
Addendum 5 is issued 8/2/2024 to incorporate document revisions and questions and responses.
Addendum 6 is issued 8/14/2024 to incorporate document revisions and questions and responses, as well as to extend the due date for questions until 8/22/2024.
Addendum 7 is issued 8/27/2024 to incorporate document revisions and questions and responses. The question due date and the proposal due date have also been extended.
Addendum 8 is issued 9/5/2024 to incorporate document revisions and questions and responses.
Addendum 9 is issued 9/11/2024 to incorporate document revisions and questions and responses.
Addendum 10 is issued 9/25/2024 to incorporate document revisions and questions and responses.
Addendum 11 is issued 9/27/2024 to extend the proposal due date to 12/13/2024 and the question cut-off date to 11/20/2024.
Addendum 12 is issued 10/10/2024 to incorporate document revisions and questions and responses.
Addendum 13 is issued 10/11/2024 to incorporate questions and responses.
Addendum 14 is issued 10/29/2024 to incorporate document revisions and questions and responses.
Addendum 15 is issued 11/08/2024 to extend the proposal due date to 2/7/2025 and the question cut-off date to 1/15/2025 and to incorporate document revisions. This action originally indicated "2024" as the year for the new due dates and is corrected with a follow-up modification to this Addednum 15 posting, reflected in the "LBNF-ND-350921-BWQ Addendum 15 Rev 1" revised document.
Addendum 16 is issued 11/22/2024 to incorporate document revisions and questions and responses.
Attachments/Links
Contact Information
Contracting Office Address
- Kirk Rd. & Pine St.
- Batavia , IL 60510
- USA
Primary Point of Contact
- Brian Quinn
- bquinn@fnal.gov
- Phone Number 6308405777
Secondary Point of Contact
- Craig Schmitz
- schmitzc@fnal.gov
- Phone Number 6308403998
History
- Apr 03, 2025 10:55 pm CDTSolicitation (Updated)
- Mar 04, 2025 12:06 pm CSTSolicitation (Updated)
- Feb 03, 2025 02:40 pm CSTSolicitation (Updated)
- Jan 30, 2025 03:23 pm CSTSolicitation (Updated)
- Jan 24, 2025 02:55 pm CSTSolicitation (Updated)
- Jan 21, 2025 08:16 pm CSTSolicitation (Updated)
- Jan 14, 2025 12:34 pm CSTSolicitation (Updated)
- Dec 11, 2024 04:24 pm CSTSolicitation (Updated)
- Nov 22, 2024 02:29 pm CSTSolicitation (Updated)
- Nov 08, 2024 03:30 pm CSTSolicitation (Updated)
- Nov 08, 2024 01:50 pm CSTSolicitation (Updated)
- Oct 29, 2024 09:44 am CDTSolicitation (Updated)
- Oct 11, 2024 01:47 pm CDTSolicitation (Updated)
- Oct 10, 2024 03:12 pm CDTSolicitation (Updated)
- Sep 27, 2024 12:51 pm CDTSolicitation (Updated)
- Sep 25, 2024 03:14 pm CDTSolicitation (Updated)
- Sep 11, 2024 04:54 pm CDTSolicitation (Updated)
- Sep 05, 2024 03:17 pm CDTSolicitation (Updated)
- Aug 27, 2024 04:26 pm CDTSolicitation (Updated)
- Aug 14, 2024 12:37 pm CDTSolicitation (Updated)
- Aug 02, 2024 04:57 pm CDTSolicitation (Updated)
- Aug 01, 2024 05:26 pm CDTSolicitation (Updated)
- Jul 26, 2024 05:55 pm CDTSolicitation (Updated)
- Jul 09, 2024 09:04 pm CDTSolicitation (Updated)
- Jun 21, 2024 05:14 pm CDTSolicitation (Updated)
- Jun 05, 2024 03:55 pm CDTSolicitation (Original)
- May 09, 2024 10:55 pm CDTPresolicitation (Updated)