MT FLAP BOR 2980(1), Sun River Bridge Replacement
Award Details
- Contract Award Date: Jan 13, 2025
- Contract Award Number: 69056725C000006
- Task/Delivery Order Number:
- Contractor Awarded Unique Entity ID: EJDKU2KTJE61
- Contractor Awarded Name: Hamilton Construction CO
- Contractor Awarded Address: Springfield, OR 97477 USA
- Base and All Options Value (Total Contract Value): $16,391,289.00
General Information
- Contract Opportunity Type: Award Notice (Original)
- Original Published Date: Jan 13, 2025 07:35 pm EST
- Inactive Policy: Manual
- Original Inactive Date: Feb 13, 2025
- Initiative:
- None
Classification
- Original Set Aside:
- Product Service Code:
- NAICS Code:
- 237310 - Highway, Street, and Bridge Construction
- Place of Performance: Augusta , MT 59410USA
Description
MT FLAP BOR 2980(1), Sun River Bridge Replacement
Helena-Lewis and Clark National Forest, Lewis and Clark County, Teton County, Montana
The work consists of building a new bridge about 200 feet downstream of the existing bridge, with new approach. The approaches are on embankments and MSE wall approaches. Final surfacing will be gravel for approaches and concrete on the bridge.
The project includes construction of a 3 span, 462-foot long precast-post-tensioned girder bridge with a precast concrete deck. Abutments are founded on both spread footing and piles within an MSE wall fill. Piers are supported on 10 foot diameter drilled shafts. The work may include as an Option demolition of the existing steel truss bridge upon completion of the new structure.
Project length: 0.36 miles
Attachments/Links
Contact Information
Contracting Office Address
- DOT FEDERAL HIGHWAY ADMIN 610 E FIFTH STREET
- VANCOUVER , WA 98661
- USA
Primary Point of Contact
- Contracts G. Office
- contracts@mail.wfl.fhwa.dot.gov
- Phone Number 3606197520
- Fax Number 3606197932
Secondary Point of Contact
History
- Feb 13, 2025 11:55 pm ESTAward Notice (Original)
- Nov 21, 2024 03:20 pm ESTSolicitation (Updated)